Modular, pre-assembled conveyor trestles, gallery lattice bridges and transfer towers moving diamond ore across rough Kalahari terrain — designed for containerised assembly with zero on-site welding.
Skilled coded welders are scarce and expensive in the Kalahari, and mobilising a welding crew for 4.2 km of gallery would have dominated the project budget. Ambient dust also makes field welding quality difficult to guarantee.
We re-engineered the conveyor gallery as a fully bolted system: 312 modules, each sized to a standard 12 m flat-rack, with HSFG bolted splices and direct tension indicators in place of every field weld. Modules were shop-assembled, galvanized and match-marked, then shipped in erection sequence so the site crew could build straight off the truck.
Erected by a semi-skilled local crew with a torque-wrench methodology and no field welding whatsoever. The bolted approach cut site labour cost by an estimated 40 % against a welded equivalent.
Ready to build?
Send us your drawings, Tekla model or project scope. Our estimation bureau responds to complete RFQs within 24 hours.